The initial planning stages commenced in late 2019 and continued into Feb of 2020. Both Luke & Joel had a great input and gave us excellent guidance and direction in ensuring that the finished product, was going to be the Kitchen we had waited years to install.
Joel issued an installation programme in late Feb in which all works were going to commence on March 21st 2020, with all works being completed within 14 - 16 days. Due to the extent of the works, the kitchen and front room were also being knocked into one by Kitchen Lift, as a kitchen dinner. All works were planned to be carried out when we were on holiday in SA.
Between 23rd Jan & 19th March 20 we paid a total of £8,112.27 up front payments to get materials ordered and as we were going to be out of the country. The balance was to be paid upon completion of the works upon our return. Then on the 19th March our holiday was cancelled, and shortly there after the country went into the initial Covid lockdown.
Therefore as no one new the full extent and potential delay in the installation of the kitchen etc, I requested on 25th March a refund of the monies pre paid. of this money only £3,750.00 was returned. When I clarified this with Luke he confirmed in an email dated the 25th March that ''I'll get the remaining amount to you when I can'' (£4,365.27) minus £462.27 for flor tiles which had already been delivered to the house.
This money was never paid back to ourselves!! However we did not pursue as we intended to get the work carried out as soon as the lockdown was lifted. And again we did not exposed and at risk because of the professional way they had dealt with ourselves in the planning of the work.
8th June works commenced, and that is when the NIGHTMARE commenced!!!!!
Not showing up for days on end with endless promises.
When they did show, they would be there for minutes let alone a few hours on 90% of occasions before leaving and not returning for any number of days.
When they actually did show up, leaving and absolute mess at the end of the day, making no attempt to clean up after themselves. Not even their own tools, which we just left where they were used, this included both externally of the house as well as internally.
Boxed Kitchen units / materials left out on the drive in all weathers for weeks on end, with no attempt to protect them, and then trying to install them into our house!
Absolutely gobsmacking!!!
It all came to a head in September after 12 weeks, where we had had enough and threw Joel out of the house as the workmanship was the to bad to ignore. Everything that he was touching, we knew we were going to have to put right.
Luke, came to the house that evening and tried in vain to distance himself from the poor standard workmanship. Units already swelling up due to water damage / 40m2 of floor tiles had to be removed and refitted due to poor quality of fitting / island and units had to be taken out and refitted etc etc. He recognised and accepted the issues and said that he only had one sub contractor that he could 'trust' to put the issues right, as he 'could not trust any of his other fitters due to their standard of work'.
It was agreed between us that we would not be paying him for the kitchen, and that any monies 'in principal owed' that we would pay another fitted to cover the cost of putting it right. He also confirmed that in recognition of the stress / hassle and all round poor service we had received, that he would also cover the cost of replacement panels etc with the sub contractor. He also confirmed that all works would be completed by the end of the month (September 20).
Mid October 20 (6 months after commencing) and still nothing had been done to resolve the situation. He informed the sub contractor that he would NOT be paying for any replacement panels and that he wanted nothing more to do with the works, thus leaving us to it! Absolutely Unbelievable!!
We then proceeded to engage with the sub contractor directly, and the works re commenced in December 2020. With works expected to be completed in early Feb 21. The standard of workmanship / communication / reliability is on a different level to Kitchen Lift.
• Whole Kitchen had to be dismantled and what units could be saved were re used.
• All newly installed google lighting system, had to be removed along with the kitchen
• Island had to be dismantled.
• Whole 40m2 floor area of tiles and sub floor had to be taken up and skipped.
At every stage of the works I have taken countless photographs of the poor standard of all aspects of their work, and have no issues in sharing of line.